How to Protect Payments When BuyingOff-Plan Property: Legal Safeguardsand Risks
Purchasing property during the construction phase can be attractive to investors, but it also involves risks that do not arise when buying a completed property. At the time of the first payment, the building may exist only on architectural plans, certain permits may still be pending, and completion may depend on the developer, contractors and regulatory procedures.
Protecting an investor in an off-plan transaction therefore begins not with assessing potential returns, but with a more fundamental question: what happens to my money if the project is delayed, altered or never completed?
At Trustmont Capital, we consider payment structures, contractual safeguards and legal due diligence as interconnected elements of investment protection. The specific mechanisms available depend on the legislation of the relevant country, local market practices and the project’s stage of development.
What Payment Protection Mechanisms Are Used in Off-Plan Transactions?
There is no universal protection mechanism that operates in the same way across all markets. Depending on the jurisdiction and project structure, the following safeguards may be available:
- Staged payments linked to actual construction progress.
- Refund provisions where the necessary permits are not obtained.
- Retention of part of the purchase price until the property is ready for lawful occupation.
- Registration of rights or preliminary agreements.
- Escrow accounts.
- Proper documentary evidence of every payment.
- Contractual liability for the developer’s failure to fulfil its obligations.
The fundamental principle is that investors should not be paying solely for the promise of a future outcome. Payments should be linked to specific events that can be legally or factually verified.
1. Staged Payments Linked to Construction Progress
One of the most widely applicable mechanisms is a construction-linked payment plan, under which payments are tied to the actual completion of construction milestones.
For example, the next payment may be conditional upon:
- Obtaining a building permit.
- Completion of the foundations.
- Completion of an agreed stage of structural works.
- Completion of the façade.
- Completion of the main internal works.
- Obtaining the necessary approvals for occupation or use.
Importantly, payments should not depend solely on calendar dates. We recommend establishing two conditions that must be satisfied together:
- The agreed payment date or payment period has been reached.
- The developer has provided adequate evidence that the relevant construction milestone has been completed.
Such evidence may include photographs, video footage, completion certificates, technical reports or an assessment by an independent engineer.
If the relevant stage has not been completed, or the developer has failed to provide the evidence required under the contract, the investor should have a contractual right to suspend the next payment without incurring penalties. This helps reduce the risk of investors continuing to finance projects where construction progress has effectively stopped.
What If Building Permits Have Not Yet Been Obtained?
Projects at a very early stage of development require particular attention. If an investor commits funds before the necessary permits have been issued, the agreement should clearly establish:
- A final deadline for obtaining the required permits.
- Any permitted short grace period.
- The investor’s right to withdraw from the transaction if the permits are not obtained.
- The procedure for refunding payments already made.
- The deadline for issuing such refunds.
- Liability for late repayment.
For example, if the required permits are not obtained within the agreed period, the investor may have the right to terminate the agreement unilaterally and recover all amounts previously paid.
Importantly, the right to a refund should not depend on a verbal assurance. It should be expressly documented in the contract.
Why Should Investors Avoid Paying 100% Before Project Completion?
Physical completion of construction does not necessarily mean that a property is legally ready for occupation, use or transfer to the investor. Outstanding matters may include:
- Unresolved permit requirements.
- Discrepancies with approved project documentation.
- Missing occupancy or operational approvals.
- Unfulfilled legal requirements for transferring ownership or leasehold rights.
For this reason, it may be appropriate to retain a portion of the purchase price until the legally required documentation has been obtained and the property is ready for transfer.
In other words, the investor should receive not merely a completed building, but a property that is legally suitable for its intended use and transfer.
Registration of Investors’ Rights
Where the legislation of a particular country permits or requires the registration of relevant rights or obligations, registration may provide an additional layer of protection.
For example, in Georgia, preliminary sale and purchase agreements may be registered with the National Agency of Public Registry under the Ministry of Justice. In such circumstances, the investor’s connection to a specific future property becomes part of the public record.
This may:
- Reduce the risk of the same property being sold twice.
- Strengthen the investor’s evidential position.
- Formally record the investor’s interest in the relevant property.
However, the availability and legal consequences of registration must always be assessed under the laws of the relevant jurisdiction.
Escrow Accounts: How Does This Additional Protection Work?
Escrow arrangements provide a specific legal framework for holding and using funds.
A notable example is the United Arab Emirates, where a regulated system of project escrow accounts applies to relevant off-plan developments.
However, it is important to distinguish between traditional escrow arrangements, under which funds are held until specified conditions are met, and project escrow arrangements, which permit construction financing in accordance with applicable regulations.
In other markets, the availability of escrow arrangements depends on local legislation, the developer’s financial model and the specific agreements between the parties.
Documentary Evidence of Every Payment
Even a carefully structured payment schedule may provide insufficient protection if individual payments are not properly documented. For every payment, it is important to retain documentary evidence establishing:
- Who received the funds.
- The legal basis for the payment.
- The agreement to which the payment relates.
- The amount paid.
- The date on which the funds were received.
This includes not only invoices but also receipts or other documents confirming that funds have actually been received under the relevant investment agreement.
Where possible, such documentation should be obtained not only electronically but also as original documents bearing the appropriate signatures of authorised representatives and official stamps, where applicable.
This is important beyond accounting purposes. In the event of a dispute, payment documentation may form part of the evidence supporting a claim for repayment or compensation.
What Might a More Secure Payment Schedule Look Like?
An illustrative example of an off-plan transaction structure:
| Milestone | Share | Payment condition |
|---|---|---|
| Signing of the agreement | 20% | Proper execution of the agreement |
| Obtaining the building permit | 10% | Provision of the permit and supporting documents |
| Completion of foundations | 20% | Evidence of completed works |
| Completion of main structural works | 20% | Documentary confirmation of progress |
| Façade and principal internal works | 20% | Confirmation of the agreed milestone |
| Occupancy approval / readiness for handover | 10% | Required occupancy documentation and confirmation of readiness |
This is an illustrative example rather than a universal standard. The appropriate payment schedule depends on the country, the project, the developer and the structure of the transaction.
The agreement should also specify who is responsible for confirming completion of each milestone, how such confirmation is provided, how much time the investor has to review the evidence, and what happens if the developer fails to satisfy the relevant condition.
Key principle: postponing a payment because the developer has not fulfilled an agreed condition should not automatically constitute a payment default by the investor.
What Should Be Verified Before the First Payment?
Even the most carefully designed payment schedule cannot replace legal due diligence on the project itself. Before making the first payment, we recommend conducting Legal Due Diligence covering, at a minimum, the following areas.
The Developer and Recipient of Funds
It is essential to establish who will receive the money, whether that legal entity has authority to enter into the agreement, and how it is connected to the developer and the landowner.
The review should also examine the company’s current legal status, the authority of the signatory, available financial information and the legal relationships between the entities involved.
The Land
The following matters should be verified:
- Legal ownership of the land.
- Permitted land use.
- Zoning.
- Compliance of the proposed development with applicable restrictions.
- Mortgages.
- Legal seizures or attachment orders.
- Easements.
- Other encumbrances.
Permits and Project Documentation
The review should assess the validity of relevant permits, licences, architectural documentation and cadastral records, together with their consistency with the proposed development.
Contractors
It is important to establish who is actually responsible for construction, the contractual relationship between the developer and the main contractor, and whether the required professional authorisations or licences are in place.
Actual Construction Progress
Where possible, an inspection of the construction site should be undertaken with the involvement of local representatives. This is particularly important for investors based in another country.
Local Legal Expertise
Complex or unusual transactions may require local legal professionals to examine public registers, litigation records and applicable legal restrictions.
The outcome of legal due diligence should extend beyond a checklist of documents. It should provide an assessment of the project’s strengths and weaknesses, identify key risks and outline practical measures to mitigate them.
Our principle: verify first, pay second.
What Should Be Checked When Investing in Hotel Property?
An additional level of verification is required when an investor purchases property within a hotel development operating under an international brand.
Where a project claims an association with a brand such as Wyndham or Radisson, the existence and legal basis of that relationship should be verified through appropriate documentation, including licensing, franchise or management agreements.
The appearance of a recognised brand in a developer’s presentation is not, in itself, evidence of a legally established partnership.
The hotel management company should also be assessed, including:
- Its experience.
- Its reputation.
- The management agreement.
- Management fees.
- Operating expenses.
- Income distribution arrangements.
- The parties’ respective responsibilities.
- Consistency between contractual terms and the proposed financial model.
Which Warning Signs Should Concern Investors?
An individual warning sign does not necessarily indicate that a project is problematic. However, several warning signs occurring together may justify more extensive due diligence or reconsideration of the transaction’s terms.
1. The Developer Repeatedly Delays Providing Documents
Confidentiality may legitimately apply to certain documents. However, repeated avoidance of information requests or the absence of clear timelines for providing documentation warrants further investigation.
2. Poor Communication
If a developer fails to respond to enquiries, does not honour commitments or avoids explaining legal and technical matters before receiving funds, this may indicate potential communication problems later.
3. Difficulty Negotiating the Agreement
Contract negotiations can reasonably take time. However, disregarding justified legal amendments, failing to provide reasoned responses or refusing to discuss fundamental investor protections should be regarded as warning signs.
4. Inconsistent Information and Excessive Promises
If project representatives provide conflicting construction timelines, budgets or specifications, or if projected returns cannot be substantiated by the agreement or financial model, the investor should consider pausing the transaction and conducting additional checks.
Marketing materials should not be treated as equivalent to legally enforceable commitments. Other potential warning signs include:
- Requests to transfer funds to third parties without a clear legal basis.
- The absence of clearly defined construction completion deadlines.
- No specified timeframe for transferring ownership rights.
- A developer’s refusal to accept contractual liability for breaches.
- Unclear refund procedures.
- Significant land encumbrances without a clear mechanism for their release.
- Discrepancies between actual construction, approved documentation and the developer’s representations.
How Can Investors Distinguish Legal Protection from Marketing Promises?
High returns, guaranteed profits, buyback arrangements, an international brand or promises of rapid capital appreciation may form part of a commercial proposition.
However, investors should ask a different question: Where exactly is this commitment documented, and what happens if it is not fulfilled?
Where a commitment has financial significance, it should be properly structured and incorporated into legally binding documentation.
Investment analysis should therefore consider not only potential profitability but also legal, financial and operational risks.
Conclusion
A more secure off-plan investment involves more than selecting a reputable developer.
It requires a comprehensive protection framework incorporating legal due diligence, an appropriately structured agreement, staged payments, verification of actual construction progress, documentary controls and clearly defined remedies in the event of contractual breaches.
Perfect projects are exceptionally rare. Every development has its own strengths, weaknesses, limitations and risks.
The responsibility of a professional adviser is not to conceal these risks behind marketing claims, but to provide investors with a complete and objective picture that supports informed decision-making.